Schedule of our lease assets and our lease liabilities

The following table reflects our lease assets and our lease liabilities at March 31, 2025 and December 31, 2024 (in thousands):

    

March 31, 

    

December 31,

2025

2024

Assets:

Operating lease right-of-use assets

$

515

$

536

Liabilities:

 

  

 

  

Operating lease liabilities, current

$

111

$

106

Operating lease liabilities, non-current

$

523

$

553

Schedule of components of lease costs

The components of lease costs were as follows (in thousands):

March 31, 2025

March 31, 2024

Operating lease cost

$

47

$

53

Short term lease cost

8

8

Total lease cost

$

55

$

61

Schedule of maturity of operating lease liabilities

As of March 31, 2025, the maturity of operating lease liabilities was as follows (in thousands):

Payments due in:

 

Year ending December 31, 2025 (9 months remaining)

 

$

138

Year ending December 31, 2026

 

189

Year ending December 31, 2027

194

Year ending December 31, 2028

200

Year ending December 31, 2029

103

Total minimum lease payments

824

Less: Amounts representing interest

 

(190)

Present value of capital lease obligations

$

634

Schedule of lease term and discount rate

    

March 31, 2025

Weighted-average remaining lease term (in years)

 

4.25

Weighted-average discount rate

 

13.0

%

Schedule of supplemental cash flow information related to leases

Supplemental cash flow information related to leases was as follows (in thousands):

    

Three Months Ended

March 31, 2025

Operating cash outflows from operating leases

$

45